StarDust Ranch News (Updated December 26th 2011)
As we wind down 2011, our third site project, the septic system has been completed. Our initial goal (Phase 1), was to complete the three necessary site improvements at SDR by the end of 2011. The improvements are power, water, and sanitary system. All have been achieved, including the costly running of all power/electrical lines underground, the outcome being 360 degrees of unobstructed views. Additionally......

1. Steve Cooper’s observatory is fully operational and he is in the process of fine tuning his equipment.

2. John Nemcik’s observatory continues to move forward and the latest accomplishments are as follows:
A. All interior and exterior finishes are completed. B. Warm room is ready for flooring and cabinetry. C. Water and Septic supply lines are in. D. Heating and cooling system installed ( I went with the Mitsubishi Split System). E. Telescope room anxiously awaits the arrival of the ASA DDM85  

3. Tony Menendez recently took possession of a beautiful new RV and is in the process of setting up and fine tuning his equipment

Happy New Year and God Bless!...........John Nemčik

Note: Many of the web page features below are currently linked to interim/dummy loading. In example, live weather info is linked to a commercial weather site, not to actual weather equipment on site at SDR .  As each aspect or device is installed and functioning, the proxy will be removed and actual device put into place. Currently the Clear Sky Clock is in place for SDR.
Observatory Control Page

Remote Observatory Control

StarDust Ranch Info & Observatory Control Portal

StarDust Ranch

Clear Sky Clock